Project Description

Following Tropical Storm Irene, a wooded embankment between Cold River Road and the Cold River became increasingly unstable, to the point where it endangered a section of this critical Town highway. OCE conducted a topographic survey and developed a topographic base plan including existing and proposed right-of-way limits. After a kickoff meeting to discuss the overall project, OCE prepared a preliminary (and with approval from the Town) and final design, including culverts, design details, and grading. After preparing a State of Vermont Construction General (Erosion Control) Permit and Town Subdivision Application, OCE administered the bid phase and provided both Construction Observation and Review to ensure the project was completed in conformance with contract documents and on budget.