Berlin Water System Moves Forward

The new $5.5M Berlin Municipal Water System is 60% complete and progressing smoothly and on schedule. The project includes a 400,000 gallon water storage tank, six miles of water mains, three wells, and a well pump control building. Munson Earth Moving, of Williston, is the General Contractor. Jeff Mangini and Jess Buckley of OCEĀ are on site as resident project representatives. Construction will be complete in December.